The brickwork was complete, scaffold lifted and top fascia and gutter was installed on 16 October. The roof tiles were also installed the week after on 23 October, but because we were about 20 tiles short, they came back the following week to finish off the job. It's been raining quite a bit this week, but fortunately, that hasn't really affected the progress. Our Site Supervisor said we'll be ready for a pre-lining inspection in another 2-3 weeks from now. Hoping we'll already be in the Lock Up stage before the Construction team takes a much deserved break over Christmas.